Access Key     Description
1Home Page
| Home Page |

 

Elgin Gas Release

15 April 2012

Introduction

Total S.A. is a large multinational oil and gas company created in France in March 1924, they employ over 90,000 people worldwide and operate in over 130 countries. They have interests in the oil and gas industry upstream and downstream, as operators or in joint ventures with other oil and gas companies such as Esso, Texaco, etc.

A subsidiary of the Total group is Total E&P UK PLC, one of the UK’s largest oil and gas operators. They operate several installations including Alwyn North, Dunbar, Ellon, Elgin and Franklin fields. Since 2002 they have had ten improvement notices from HSE, two of which were for the Elgin Franklin in 2006 and no prosecutions.

Purpose

The purpose of this note is to apprise interested parties of the background to and on-going status of the gas release incident of 25th March 2012 and to capture key lessons in due course

Elgin/Franklin              

The Elgin field is a high pressure high temperature field located in the Graben Area, of the central north sea around 240Km from Aberdeen. It was discovered in 1991 at a depth of around 93 metres. The combination of high pressure  and high temperature was a difficult challenge for Total at that time and resulted in the design of the ESDVs (emergency shutdown valves) taking  five years and at the time they were the largest in the world. Drilling on the five production wells and reconnecting two exploration wells, was carried out by the Santa Fe Galaxy 1 with well pressures between 650 -1100 Bar.

Production commenced from the Elgin field  in March 2001 with gas being exported from May that year, within 12 months the Elgin and Franklin fields combined provided 13 million m3 /day of gas and 140,000 barrels of condensate,  combined equating to 220,000 of oil. The well head platform is a steel jacket four leg design connected to the production, utilities and accommodation (PUQ) platform by a bridge. The well head platform is normally unmanned and operated from the PUQ control room as is the Franklin well head platform. Gas from the Elgin field is exported via the SEAL pipeline to Bacton and into the UK national grid. Gas from the Franklin and Shearwater also is exported using the same route.

On the 25th March 2012 around noon well control problem resulted in a gas release, and the decision to evacuate non essential personnel from the platform and neighbouring Rowan Viking drilling Jack up was made.

A sequence of Total events is listed at the end of this article based on the press releases on the total incident web site, other significant events are precautionary down manning of non- essential personnel on the neighbouring Shearwater and Hans Van Duel installations

Incident related articles

Total Stops Elgin Gas Leak

Total Begins Elgin Well-Intervention Operation

Total Incident website

Elgin leak 'signals decommissioning woe'

Total prepares parallel operations to stop Elgin gas leak

Gas cloud encircles Total's Elgin-Franklin platform- union

No Indication Total Gas Leak has had Significant Environmental Impact

Advanced Drilling in HP/HT: Total’s Experience on Elgin/Franklin (UK North Sea)

Elgin-Franklin hub was producing 10% of UK's gas before leak

Shell completes shutdown

Total knew of gas leak fears four weeks ago

Incident chronology based on Total press releases

Date/Time

Events

25/03/12

~ 12:15

Gas release

~14:00

Evacuation

~16:45

Viking personnel evacuation onshore, Non essential PUQ personnel evacuated to neighbouring platforms

~18:45

Efforts to control release, non essential PUQ personnel moving to onshore

~23:00

All 238 Personnel accounted for no injuries, 150 personnel onshore, 69 neighbouring platforms, 19 crew still on PUQ,

OPEP activated,

Sheen on water seen

26/03/12

 

~03:28

19 core PUQ crew evacuated onshore, air spotter plane due 07:30 for sheen

~14:25

Experts being mobilised to assist

~21:00

Situation stable,  no change in sheen size/composition,

SOSRep mobilised

28/03/12

 

~16:00

Gas cloud visible from spotter plane, sheen unchanged, fire fighting and ROV vessels on standby, cause still unknown

~18:25

Lit flare burning wind direction away from gas cloud

29/03/12

 

~19:00

Gas leak ongoing, well experts mobilised, thought leak from well formation above reservoir, volume gas unknown moving away from platform

30/03/12

 

~13:30

Two potential solutions to leak blocking the well and relief well drilling

~18:30

Situation stable five days,

Two main solutions are being progressed. The first is to pump heavy mud directly into the well and the second is to drill relief wells to intervene at the source of the gas flow,

Sedco 714 and Rowan Gorilla V available to drill relief wells,

gas leak estimate to be around 200 000 m3 of gas per day,

Exclusion zone set up

Sheen reducing in size

Flare diminishing

31/03/12

 

~12:00

Flare extinguished

02/04/12

 

~12:00

Talks to board platform

05/04/12

 

~10:30

Helicopter dispatched to platform with well control team

~17:45

Well control specialists boarded platform and carried out survey

06/04/12

 

 

No gas was found on the PUQ or access to, well head 90m away

15/5/12 Oil is pumped into well
16/5/12 Oil leak stopped